Weekly Project Update – September 10, 2021
The following work is scheduled over the next three weeks:
Garden State Parkway Mileposts 140 to 143
On November 14, 2020, traffic on the Northbound Garden State Parkway between mileposts 140.9 and 142.1 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced.
On November 21, 2020, traffic on the Southbound Garden State Parkway between mileposts 141.0 and 142.2 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced.
On or about September 20, 2021, traffic on the Northbound Garden State Parkway between mileposts 140.9 and 142.1 will be shifted to a new traffic pattern. All existing travel lanes will remain open, but lane widths will be reduced.
On or about September 20, 2021, traffic on the Southbound Garden State Parkway between mileposts 141.0 and 142.2 will be shifted to a new traffic pattern. All existing travel lanes will remain open, but lane widths will be reduced.
Portable VMS boards with advanced warning messages will be deployed six days prior to the traffic shift on the Northbound Roadway near MP 139.3 and Southbound Roadway near MP 143.0.
The installation of the new traffic pattern will be performed under temporary nightly lane closures.
There will also be temporary half-ramp closures of the exit ramps at Northbound 139A, 139B and 140 and Southbound 141 in order to install the new traffic pattern, but the exit ramps will remain open at all times.
Installation of beam guide rail and guide rail attachments along Southbound Garden State Parkway Roadways was completed on September 9, 2021.
Asphalt paving of bridge approaches at Structures 141.3, 141.7 and 141.9 along Southbound Garden State Parkway Roadways was completed on September 8, 2021.
On or about September 20, 2021, temporary striping for the Stage 2 traffic shift will begin along the Northbound Garden State Parkway Roadway. This work will require lane closures on the Northbound Garden State Parkway from 9:00 PM to 6:00 AM.
On or about September 20, 2021, temporary striping for the Stage 2 traffic shift will begin along the Southbound Garden State Parkway Roadway. This work will require lane closures on Southbound Garden State Parkway from 9:00 PM to 6:00 AM.
Bridge No. 140.2, GSP under Galloping Hill Road
On April 6, 2021, removal of existing timber shielding and installation of new timber shielding and other temporary support structures under the bridge began and will continue throughout the month of September 2021. This work will require periodic single lane to three lane closures on either the Northbound or Southbound Garden State Parkway from 9:00 PM to 6:00 AM.
On or about September 20, 2021, installation of utility supports and conduits for PSE&G and Verizon lines will begin and will continue throughout the month of September 2021. This work will require periodic single lane to three lane closures on either the Northbound or Southbound Garden State Parkway from 9:00 PM to 6:00 AM.
Bridge No. 141.3, GSP over Route 22 EB
On May 10, 2021, substructure repairs at the South abutment of Structure 141.3 began and will continue throughout the month of September 2021. This work may require periodic single lane closures on Route 22EB from 8:00 PM to 5:00 AM.
On June 23, 2021, bearing replacement along North abutment of Structure 141.3 began and will continue throughout the month of September 2021. This work may require periodic single lane closures on Route 22EB from 8:00 PM to 5:00 AM.
Removal of timber shielding and other temporary support structures under the bridge within Stage 1 will continue throughout month of September 2021. This work may require periodic single lane closures on Route 22 EB from 8:00 PM to 5:00 AM.
Bridge No. 141.7, GSP over Morris Avenue (Route 82)
Substructure repairs at the pier of Structure 141.7 was completed on September 3, 2021.
On June 30, 2021, bearing replacement at Structure 141.7 began and will continue throughout the month of September 2021. This work may require periodic single lane closures on Route 82WB from 7:00 AM to 3:00 PM.
Removal of timber shielding and other temporary support structures under the bridge within Stage 1 will continue throughout month of September 2021. This work may require periodic single lane closures on Route 82 EB and WB from 7:00 AM to 3:00 PM.
Bridge No. 141.9, GSP over Route 22 WB
Removal of timber shielding and other temporary support structures under the bridge within Stage 1 will continue throughout month of September 2021. This work may require periodic single lane closures on Route 22 WB from 8:00 PM to 5:00 AM.