Weekly Project Update – April 9, 2021

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On November 14, 2020, traffic on the Northbound Garden State Parkway between mileposts 140.9 and 142.1 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced. 

On November 21, 2020, traffic on the Southbound Garden State Parkway between mileposts 141.0 and 142.2 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced. 

Bridge No. 140.2, GSP under Galloping Hill Road

On April 6, 2021, removal of existing timber shielding and installation of new timber shielding and other temporary support structures under the bridge began and will continue throughout the month of April 2021. This work will require periodic single lane to three lane closures on either the Northbound or Southbound Garden State Parkway from 9:00 PM to 6:00 AM.

Bridge No. 141.3, GSP over Route 22 EB

Abrasive blasting (surface preparation) and application of zinc primer on structural members at Structure 141.3 SB was completed on April 9, 2021.

Installation of electrical conduit for new underbridge lighting will continue throughout the week of April 12, 2021. This work may require periodic single lane closures on Route 22EB from 8:00 AM to 3:00 PM.

On or about April 13, 2021, installation of steel bolsters and end diaphragms in Stage 1 at Structure 141.3 in the Northbound direction will begin. This work will not require lane closures.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

On or about April 9, 2021, installation of steel reinforcement for the bridge deck in Stage 1 at Structure 141.7 in the Northbound and Southbound directions will begin. This work will not require lane closures.

On March 29, 2021, installation of electrical conduit for new underbridge lighting began and will continue throughout the month of April. This work may require periodic single lane closures on Route 82 WB from 7:00 AM to 3:00 PM.

Bridge No. 141.9, GSP over Route 22 WB

On March 22, 2021, installation of the temporary supports and jacks for structural jacking at the South abutment of Structure 141.9 NB began and will continue until April 16, 2021. This work may require periodic single lane closures on Route 22WB from 8:00 AM to 3:00 PM.

On March 29, 2021, installation of electrical conduit for new underbridge lighting began and will continue throughout month of April. This work may require periodic single lane closures on Route 22WB from 8:00 AM to 3:00 PM.

On or about April 12, 2021, abrasive blasting (surface preparation) and application of zinc primer on structural members at Structure 141.9 NB will begin. This work will not require lane closures.

Previous
Previous

Weekly Project Update – April 16, 2021

Next
Next

Weekly Project Update – April 2, 2021