Weekly Project Update – July 4, 2024
The following work is scheduled over the next three weeks:
Garden State Parkway Mileposts 140 to 143
Micro-milling and sawcut grooving of bridge decks will be completed by approximately July 19, 2024. This work will require temporary lane closures during the night shift along the GSP.
Deck gland installation at 141.3, 141.7 and 141.9 is underway and will continue into mid-July.
Bridge No. 140.2, GSP under Galloping Hill Road
On June 20, 2024, cleaning and painting of structural steel began and will continue through August 8. This work will require temporary lane closures during the night shift along the GSP NB/SB.
On or about July 1, 2024, the south sidewalk on GHR will begin construction.
On or about July 1, 2024, the temporary pedestrian walkway and overhang bracket on the south fascia of Structure 140.2 will be removed. This work will require temporary lane closures during the night shift along the GSP NB/SB. This work will be completed by approximately July 12, 2024. The overhang on the north side of GHR has been removed.
On or about July 15, 2024, traffic on GHR will shift into stage 5A. Traffic on Galloping Hill Road has been shifted to a new traffic pattern (Stage 4) with reduced lane widths.
Bridge No. 141.3, GSP over Route 22 EB
Spall repairs will commence under Structure 141.3 on July 1, 2024, and be completed by approximately July 8, 2024. This will require nightly lane closings on Rt 22 EB.
Bridge No. 141.7, GSP over Morris Avenue (Route 82)
No work is scheduled at this location.
Bridge No. 141.9, GSP over Route 22 WB
No work is scheduled at this location.