Weekly Project Update – August 23, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

Deck gland installation at 141.3, 141.7 and 141.9 is underway and will continue into late August.

Bridge No. 140.2, GSP under Galloping Hill Road

On or about August 12, 2024, traffic on GHR will shift into stage 5 to construct the median islands and curb work at Golf Drive.

Bridge No. 141.3, GSP over Route 22 EB

Spall repairs will commence under Structure 141.3 on July 30, 2024, and be completed by approximately August 31, 2024. This will require nightly lane closings on Rt 22 EB.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

No work is scheduled at this location.

Bridge No. 141.9, GSP over Route 22 WB

No work is scheduled at this location.