Weekly Project Update – Sept. 15, 2023

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On September 9, 2022, traffic on the Southbound Garden State Parkway between mileposts 140.1 and 142.2 was shifted to a new traffic pattern (Stage 5, 6, and 7). All existing travel lanes remain open, but lane widths have been reduced. Portable VMS boards with advanced warning messages were deployed six days prior to the traffic shift on the Southbound Roadway near MP 138.4. The installation of the new traffic pattern was performed under temporary nightly lane closures.

On September 30, 2022, traffic on the Northbound Garden State Parkway between mileposts 140.1 and 142.2 was shifted to a new traffic pattern (Stage 5, 6, and 7). All existing travel lanes remain open, but lane widths have been reduced. Portable VMS boards with advanced warning messages were deployed six days prior to the traffic shift on the Northbound Roadway near MP 139.3. The installation of the new traffic pattern was performed under temporary nightly lane closures.

On November 16, 2022, reconstruction of existing inlets along the median barrier began. Reconstruction of existing inlets along the median barrier in Stage 5 was completed on April 28, 2023. Reconstruction of existing inlets along the median barrier in Stages 6 and 7 will continue until approximately September 19, 2023.

On March 23, 2023, installation of steel reinforcement for median barrier in Stages 6 and 7 along NB and SB Roadways began. This operation will continue until approximately September 18, 2023.

On May 16, 2023, concrete placement for median barrier in Stages 6 and 7 along the Garden State Parkway Northbound and Southbound Roadways began. This operation will continue until approximately September 19, 2023.

Construction of foundations for median barrier in Stages 6 and 7 along NB and SB Roadways will be completed by September 16, 2023.

On or about September 14, 2023, removal of MPT and shifting traffic back to original configuration on the Southbound Garden State Parkway between mileposts 140.1 and 142.2 will begin. Portable VMS boards with advanced warning messages will be deployed six days prior to the traffic shift on the Southbound Roadway near MP 138.4. This work will be performed under temporary nightly lane closures and will be completed by approximately September 23, 2023.

On or about September 21, 2023, removal of MPT and shifting traffic back to original configuration on the Northbound Garden State Parkway between mileposts 140.1 and 142.2 will begin. Portable VMS boards with advanced warning messages will be deployed six days prior to the traffic shift on the Northbound Roadway near MP 139.3. This work will be performed under temporary nightly lane closures and will be completed by approximately September 29, 2023.

On or about September 27, 2023, paving of the mainline roadway on the Southbound Garden State Parkway will begin. This work will be performed under temporary nightly lane closures.

On or about October 16, 2023, paving of the mainline roadway on the Northbound Garden State Parkway will begin. This work will be performed under temporary nightly lane closures.

Bridge No. 140.2, GSP under Galloping Hill Road

On November 9, 2022, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 1A). All existing travel lanes remain open, but lane widths have been reduced.

On or about September 18, 2023, installation of lighting on the bridge will begin.

On or about September 18, 2023, construction of temporary sidewalk along the south side of the structure will begin.

On or about September 21, 2023, paving approaches to and from bridge deck in Stage 1A and 1B will begin.

On or about September 25, 2023, traffic on Galloping Hill Road will be shifted to a new traffic pattern (Stage 2). All existing travel lanes will remain open, but lane widths will be reduced.

Bridge No. 141.3, GSP over Route 22 EB

No activities scheduled at this location at this time.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

On August 10, 2023, bearing replacement (anchor bolts) on the North and South abutments in Stage 5 at Structure 141.7 resumed. This operation will continue until approximately September 22, 2023.

Bridge No. 141.9, GSP over Route 22 WB

On September 6, 2023, repainting of structural steel at Structure 141.9 began. This operation will continue until approximately September 29, 2023. This work will require periodic single lane closures on RT 22 WB from 8:00 PM to 6:00 AM.