Weekly Project Update – October 27, 2023

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On October 10, 2023, paving of the mainline roadway on the Northbound Roadway of the Garden State Parkway began. This work will be performed under temporary nightly lane closures and will be completed by approximately October 31, 2023.

On October 19, 2023, micro-milling on bridge decks at Structures 141.3 NB, 141.7 NB, and 141.9 NB began. This work will be performed under temporary nightly lane closures and will be completed by approximately October 28, 2023.

On or about October 28, 2023, removal of MPT and shifting traffic back to original configuration on the Southbound Garden State Parkway between mileposts 140.1 and 142.2 will begin. Portable VMS boards with advanced warning messages will be deployed six days prior to the traffic shift on the Southbound Roadway near MP 138.4. This work will be performed under temporary nightly lane closures and will be completed by approximately October 29, 2023.

On or about November 1, 2023, paving of the mainline roadway on the Southbound Garden State Parkway will begin. This work will be performed under temporary nightly lane closures.

On or about November 6, 2023, micro-milling on bridge decks at Structures 141.3 SB, 141.7 SB, and 141.9 SB will begin. This work will be performed under temporary nightly lane closures and will be completed by approximately November 10, 2023.

Bridge No. 140.2, GSP under Galloping Hill Road

On November 9, 2022, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 1A). All existing travel lanes remain open, but lane widths have been reduced.

On or about November 6, 2023, traffic on Galloping Hill Road will be shifted to a new traffic pattern (Stage 2). All existing travel lanes will remain open, but lane widths will be reduced.

On or about November 7, 2023, demolition of existing bridge deck in Stage 2 will begin.

Bridge No. 141.3, GSP over Route 22 EB

Cleanup of abutments and preparation for installation of gland in expansion joints was completed on October 25, 2023.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

On August 10, 2023, bearing replacement (anchor bolts) on the North and South abutments in Stage 5 at Structure 141.7 resumed. This operation will continue until approximately November 3, 2023.

Bridge No. 141.9, GSP over Route 22 WB

Cleanup of abutments and preparation for installation of gland in expansion joints was completed on October 23, 2023.