Weekly Project Update – January 26, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On October 19, 2023, micro-milling on bridge decks at Structures 141.3 NB, 141.7 NB, and 141.9 NB began. This work is temporarily paused due to cold weather and will resume as soon as weather conditions permit.

On November 13, 2023, micro-milling on bridge decks at Structures 141.3 SB, 141.7 SB, and 141.9 SB began. This work is temporarily paused due to cold weather and will resume as soon as weather conditions permit.

Bridge No. 140.2, GSP under Galloping Hill Road

On January 11, 2024, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 3). All existing travel lanes will remain open, but lane widths have been reduced.  

On January 12, 2024, demolition of the existing bridge deck and parapet began. This work will be completed by approximately February 2, 2024.

Bridge No. 141.3, GSP over Route 22 EB

No work is scheduled at this location.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

No work is scheduled at this location.

Bridge No. 141.9, GSP over Route 22 WB

No work is scheduled at this location.