Weekly Project Update – February 23, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On October 19, 2023, micro-milling on bridge decks at Structures 141.3 NB, 141.7 NB, and 141.9 NB began. This work is temporarily paused due to cold weather and will resume as soon as weather conditions permit.

On November 13, 2023, micro-milling on bridge decks at Structures 141.3 SB, 141.7 SB, and 141.9 SB began. This work is temporarily paused due to cold weather and will resume as soon as weather conditions permit.

Bridge No. 140.2, GSP under Galloping Hill Road

On January 11, 2024, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 3). All existing travel lanes will remain open, but lane widths have been reduced.  

Demolition of the existing bridge deck and parapet was completed on February 16, 2024.

On or about February 20, 2024, installation of end diaphragms and expansion joints in Stage 3 began. This work will be completed by approximately March 5, 2024.

On or about March 6, 2024, cleaning of top flanges and application of zinc primer in Stage 3 will begin. This work will be completed by approximately March 7, 2024.

On or about March 7, 2024, installation of stay in place forms and shear connectors in Stage 3 will begin. This work will be completed by approximately March 8, 2024.

On or about March 11, 2024, installation of steel reinforcement for bridge deck in Stage 3 will begin. This work will be completed by approximately March 14, 2024.

On or about March 15, 2024, concrete placement for the bridge deck in Stage 3 will begin.

Bridge No. 141.3, GSP over Route 22 EB

No work is scheduled at this location.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

No work is scheduled at this location.

Bridge No. 141.9, GSP over Route 22 WB

No work is scheduled at this location.