Weekly Project Update – January 13, 2023

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On September 9, 2022, traffic on the Southbound Garden State Parkway between mileposts 140.1 and 142.2 was shifted to a new traffic pattern (Stage 5, 6, and 7). All existing travel lanes remain open, but lane widths have been reduced. Portable VMS boards with advanced warning messages were deployed six days prior to the traffic shift on the Southbound Roadway near MP 138.4. The installation of the new traffic pattern was performed under temporary nightly lane closures.

On September 30, 2022, traffic on the Northbound Garden State Parkway between mileposts 140.1 and 142.2 was shifted to a new traffic pattern (Stage 5, 6, and 7). All existing travel lanes remain open, but lane widths have been reduced. Portable VMS boards with advanced warning messages were deployed six days prior to the traffic shift on the Northbound Roadway near MP 139.3. The installation of the new traffic pattern was performed under temporary nightly lane closures.

On October 3, 2022, demolition of existing median barrier in stages 5, 6, and 7 began and will continue until approximately January 31, 2023.  This work may require periodic single lane closures on Garden State Parkway in the Northbound or Southbound directions from 9:00 PM to 6:00 AM.

On November 16, 2022, reconstruction of existing inlets along the median barrier began. This operation will continue until approximately January 31, 2023.

On December 20, 2022, construction of foundation for median barrier in Stage 5 along NB and SB Roadways began. This operation will continue until approximately January 31, 2023.

On or about January 16, 2023, construction of foundations for median barrier in Stages 6 and 7 along NB and SB Roadways will begin. This operation will continue until approximately February 28, 2023.

Bridge No. 140.2, GSP under Galloping Hill Road

On November 9, 2022, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 1A). All existing travel lanes remain open, but lane widths have been reduced.

On November 14, 2022, construction activities (demolition of bridge deck and installation of duct bank for PSE&G) in Stage 1A at Galloping Hill Road began. This operation will continue until approximately January 31, 2023. This work will require periodic single lane closures on Galloping Hill Road from 8:00 AM to 3:00 PM.

Bridge No. 141.3, GSP over Route 22 EB

On December 8, 2022, bearing replacement for Stage 5 at Structure 141.3 (NB/SB) began. This operation will continue until approximately January 20, 2023.

Installation of steel reinforcement for bridge parapet in Stage 5 at Structure 141.3 NB/SB was completed on January 12, 2023.

Installation of steel reinforcement for headblocks in Stage 5 at Structure 141.3 NB/SB was completed on January 13, 2023.

Installation of formwork for headblocks in Stage 5 at Structure 141.3 NB/SB was completed on January 13, 2023.

On January 13, 2023, installation of formwork for bridge parapet in Stage 5 at Structure 141.3 NB/SB began.

On or about January 16, 2023, concrete placement for headblocks in Stage 5 at Structure 141.3 NB/SB will begin. 

On or about January 17, 2023, concrete placement for bridge parapet in Stage 5 at Structure 141.3 NB/SB will begin. 

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

Concrete for bridge parapet in Stage 5 at Structure 141.7 NB/SB was placed on January 11, 2023.

Bridge No. 141.9, GSP over Route 22 WB

On or about January 16, 2023, demolition of existing bridge deck in Stage 5 at Structure 141.9 (GSP NB) will begin. This operation will continue until approximately January 20, 2023.

On or about January 23, 2023, bearing replacement and bearing area reconstruction for Stage 5 at Structure 141.9 (NB) will begin. This operation will continue until approximately January 27, 2023. This work will require periodic single lane closures on RT 22 WB from 8:00 PM to 5:00 AM.

Previous