Weekly Project Update – February 26, 2021

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

On November 14, 2020, traffic on the Northbound Garden State Parkway between mileposts 140.9 and 142.1 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced. 

On November 21, 2020, traffic on the Southbound Garden State Parkway between mileposts 141.0 and 142.2 was shifted to the left in a new traffic pattern. All existing travel lanes remain open, but lane widths have been reduced. 

On or about March 5, 2021, pothole repair work within project limits on the Northbound and Southbound Roadways will begin. This work will require periodic single or double lane closures on the Garden State Parkway.

On or about March 8, 2021, installation of anchor pins and parging joints on precast concrete construction barrier at Structures 141.3, 141.7 and 141.9 along the Southbound roadway will begin. This work will require periodic single or double lane closures on the Garden State Parkway.

Bridge No. 140.2, GSP under Galloping Hill Road

No work planned.

Bridge No. 141.3, GSP over Route 22 EB

On December 15, 2020, demolition of the parapet and bridge deck in the work zone in the Southbound direction at Structure 141.3 began and will continue throughout the months of March 2021. Periodic single lane closures on Route 22 EB from 10:00 AM to 2:00 PM may be required during demolition of concrete diaphragms at the South Abutment.

On December 23, 2020, demolition of the parapet and bridge deck in the work zone in the Northbound direction at Structure 141.3 began and will continue throughout the months of March 2021. Periodic single lane closures on Route 22 EB from 10:00 AM to 2:00 PM may be required during demolition of cap slab and concrete diaphragms at the South Abutment.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

On January 27, 2021, demolition of the parapet and bridge deck in the work zone in the Southbound direction at Structure 141.7 began and will continue until March 5, 2021. This work will not require lane closures on Route 82.

Bridge No. 141.9, GSP over Route 22 WB

On January 25, 2021, demolition of the parapet and bridge deck in the work zone in the Northbound and Southbound directions at Structure 141.9 began and will continue throughout the month of March. This work will not require lane closures on Route 22 WB.