Weekly Project Update – May 31, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

Micro-milling and sawcut grooving of bridge decks will be completed by approximately May 31, 2024. This work will require temporary lane closures during the night shift along the GSP.

Deck joint installation at Structures 141.0 and 141.2 will be ongoing in the NB and SB direction into the first week of June. This work will require temporary lane closures during the night shift along the GSP NB/SB.

Bridge No. 140.2, GSP under Galloping Hill Road

On January 11, 2024, traffic on Galloping Hill Road was shifted to a new traffic pattern (Stage 3). All existing travel lanes will remain open, but lane widths have been reduced.  

On April 29, 2024, removal of the timber shielding and other temporary supports under the bridge began. This work will require temporary lane closures during the night shift along the GSP NB/SB. This work will be completed by approximately June 7, 2024.

On May 29, 2024, the north parapet, sidewalk, and curb at Galloping Hill Road were completed.

On or about June 15, 2024, installation of bridge fence on the North parapet will be complete.

On or about June 15, 2024, traffic on Galloping Hill Road will be shifted to a new traffic pattern (Stage 4). All existing travel lanes will remain open, but lane widths will be reduced. 

On or about June 15, 2024, cleaning and painting of structural steel will begin. This work will require temporary lane closures during the night shift along the GSP NB/SB. This work will be completed by approximately July 15, 2024.

Bridge No. 141.3, GSP over Route 22 EB

No work is scheduled at this location.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

No work is scheduled at this location.

Bridge No. 141.9, GSP over Route 22 WB

No work is scheduled at this location.