Weekly Project Update – September 27, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

Deck gland installation at 141.3, 141.7 and 141.9 and final bridge striping will recommence September 9, 2024 and will continue into mid-October 2024.

Bridge No. 140.2, GSP under Galloping Hill Road

On or about September 24, 2024, final paving on GHR will commence. This work will complete by September 30, 2027.

Bridge No. 141.3, GSP over Route 22 EB

Spall repairs will commence under Structure 141.3 on July 30, 2024, and be completed by approximately October 1, 2024. This will require nightly lane closings on Rt 22 EB.

Bridge No. 141.7, GSP over Morris Avenue (Route 82)

No work is scheduled at this location.

Bridge No. 141.9, GSP over Route 22 WB

No work is scheduled at this location.

Previous
Previous

Weekly Project Update – October 4, 2024

Next
Next

Weekly Project Update – September 20, 2024