Weekly Project Update – October 4, 2024
The following work is scheduled over the next three weeks:
Garden State Parkway Mileposts 140 to 143
Deck gland installation at 141.3, 141.7 and 141.9 and final bridge striping will recommence September 9, 2024 and will continue into mid-October 2024.
Punchlist work on the Garden State Parkway will commence this week and continue through November 2024 requiring occasional nighttime lane closures on the northbound and southbound mainline..
Bridge No. 140.2, GSP under Galloping Hill Road
Punchlist work will commence this week and continue thought November 2024 requiring occasional daytime lane closures.