Weekly Project Update – October 18, 2024

The following work is scheduled over the next three weeks:

Garden State Parkway Mileposts 140 to 143

Deck gland installation at 141.3, 141.7 and 141.9 and final bridge striping will recommence September 9, 2024 and will continue into November 2024

Punchlist work on the Garden State Parkway will commence this week and continue through November 2024 requiring occasional nighttime lane closures on the northbound and southbound mainline.

Galloping Hill Road

Bridge deck grinding and grooving along with punchlist work will continue through November 2024 requiring occasional daytime lane closures on Galloping Hill Road.

Previous
Previous

Weekly Project Update – October 25, 2024

Next
Next

Weekly Project Update – October 4, 2024